Case Study - Fertilizer Plant

Fertilizer Plant fire protection 

When a nitrogen fertilizer plant experienced an explosion in an unprotected area of their plant, they quickly called F.E. Moran Special Hazard Systems to remedy the issue and keep their plant safe.

Illinois Fertilizer Plant Explosion

A nitrogen fertilizer plant in East Dubuque, IL is a primary producer of nitrogen fertilizer in the heart of the Midwest. They have been producing nitrogen fertilizer since 1965, providing low cost, environmentally conscious product.

When an explosion rocked the plant only two weeks before Christmas, they called F.E. Moran Special Hazard Systems to get the plant back in working condition. Before Christmas, F.E. Moran Special Hazard Systems accomplished that.

Christmas Deadline Creates Challenge

In early December, a gas leak in a 6-story vessel caused a major explosion. It was a wake-upvessel explosion call for the company. Wanting to prevent any future incidents, they called F.E. Moran Special Hazard Systems to install a deluge fire sprinkler system around the vessel.

F.E. Moran Special Hazard Systems designs and installs deluge systems often, but this time the obstacle arose to begin and end the project within two weeks. A nitrogen fertilizer plant needed the project to be wrapped up before Christmas, creating a challenge that F.E. Moran Special Hazard Systems was excited to take on.

Tight Timeline, Quick Turnaround

F.E. Moran Special Hazard Systems knew they had a tight timeline to maintain; Christmas was only a few weeks away. The nitrogen fertilizer plant requested a quote and by December 13, 2013, they provided it. The plant approved it and December 16, 2013, the PO was sent. The design began December 16, 2013 and was turned over December 18, 2013. The material was ordered the same day and installation began. The plant was mobilized December 20, 2013 and by December 23, 2013 the project was completed.

F.E. Moran Special Hazard Systems turned over the plant with two days to spare. Project Manager Mike Warmington said, "We had a Christmas deadline to complete a package design, materials, and labor. We dropped everything to meet their schedule, and managed to finish in seven days, getting everyone home for the holiday."

fertilizer plant  

Resource Center
News and Publications